Task(s) Task(s) Duration (days) Start Date End Date Description 30 09.01.2016 09.30.2016 Establishing company, all permits 90 01.01.2017 03.31.2017 Order equipment (2 lines) 90 01.01.2018 03.31.2018 Order equipment (2 lines) 42 06.01.2017 07.12.2017 Foundations 126 07.01.2017 11.03.2017 Buildings 42 11.04.2017 12.15.2017 Infrastructure 60 06.01.2017 07.30.2017 2 fishing vessels 450 MT 122 06.01.2017 09.30.2026 12 new vessles 42 06.01.2017 01.13.2026 6 airplanes 30 01.01.2018 01.30.2018 Expenses for Fishing season Project timeline